Vinci Construction UK Limited v Eastwood and Partners (Consulting Engineers) Limited & Anor
[2023] EWHC 1899 (TCC)
In contract claims, time does not run from the date of loss or when a claimant knew of the claim.
Limitation Act 1980, section 5
A claim under an indemnity insurance policy arises as soon as the insured event occurs, not when loss is manifested.
Callaghan v Dominion Insurance Co Ltd [1997] 2 Lloyd’s Rep 541; Colinvaux & Merkin’s Insurance Contract Law at C-0236
A claimant must show its action is not time-barred if limitation is raised by a defendant.
McGee on Limitation Periods (9th edition), paragraph 21.016
The court must consider whether a claimant has a realistic prospect of success in a summary judgment application.
Easyair v Opal Telecom [2009] EWHC 339 (Ch)
Courts should determine short points of law or construction summarily if all necessary evidence is available.
Global Asset Capital Inc v Aabar Block SARL [2017] EWCA Civ 37
In determining when a cause of action accrues under an insurance policy, the court must objectively interpret the policy language considering the background knowledge reasonably available to the parties.
Financial Conduct Authority v Arch Insurance (UK) Ltd [2021] UKSC 1
The court dismissed NHBC's application for summary judgment.
The court found that the limitation period began when Peabody had to pay more to complete the units, not when Vantage went into administration. The insured peril was the 'having to pay more', caused by insolvency, not the insolvency itself.
The court rejected NHBC's alternative argument that a claim for site security costs, incurred in 2016, rendered the whole claim time-barred.
The court found the site security cost claim (under a separate policy clause) was potentially independent from the main claim for additional construction costs and did not automatically time-bar the principal claim.
[2023] EWHC 1899 (TCC)
[2023] EWHC 2921 (TCC)
[2024] EWHC 750 (TCC)
[2023] EWHC 792 (Comm)
[2024] EWHC 1190 (TCC)