J & B Hopkins Limited v A & V Building Soltuions Limited
[2023] EWHC 301 (TCC)
An adjudicator's decision is normally enforced by summary judgment; the court doesn't assess merits, only limited grounds for resistance (e.g., material breach of natural justice).
A material breach of natural justice occurs when a substantive defense isn't considered; a peripheral issue's omission isn't material.
[Cantillon Limited v Urvasco Limited [2008] EWHC 282 (TCC), Quarterzelec Ltd v Honeywell Control Systems Limited [2008] EWHC 3315 (TCC), C & E Jacques Partnership v Ensign Contractors Limited [2009] EWHC 3383 (TCC), NAP Anglia Ltd v Sun-Land Development Co Ltd [2011] EWHC 2846 (TCC)]
Courts rarely interfere with adjudicator decisions unless the referred question is different or the process is obviously unfair.
[Carillion Construction Ltd v Devonport Royal Dockyard [2005] EWCA Civ 1358]
Adjudicators aren't obligated to detail every party's arguments or provide reasons for each conclusion unless necessary for explanation.
[Balfour Beatty Construction v Modus Corovest (Blackpool) Ltd [2008] EWHC 3029 (TCC), HS Works Limited v Enterprise Managed Services Limited [2009] EWHC 729 (TCC)]
Deliberately ignoring a defense is different from inadvertently overlooking an issue; the former may invalidate the decision, the latter usually won't.
[Pilon Limited v Breyer Group PLC [2010] EWHC 837 (TCC)]
Disregarding a party's arguments and evidence is a material breach; the court doesn't need to investigate if a different decision would have resulted, only that a real possibility exists.
[CJP Builders Limited v William Verry Limited [2008] BLR 545]
An adjudicator can breach natural justice by failing to address matters before them or not giving parties a chance to be heard, regardless of whether the decision would have differed.
[PC Harrington Contractors v Tyroddy Construction [2011] EWHC 813 (TCC)]
A stay of execution may be granted if a claimant likely can't repay, but not if their financial position is similar to when the contract was made or if it's partly due to the defendant's non-payment.
[Wimbledon Construction Company 200 Limited v Derek Vago [2005] EWHC 1086 (TCC), Bexheat Limited v Essex Services Group Limited [2022] EWHC 936 (TCC)]
Summary judgment granted to the Claimant for £49,664.80.
The adjudicator considered all defenses, even if not explicitly detailed in the decision; the Defendant didn't show a material breach of natural justice or a real prospect of successfully defending the claim; application for stay of enforcement dismissed due to insufficient pleading and lack of evidence of probable inability to repay.
[2023] EWHC 301 (TCC)
[2023] EWHC 278 (TCC)
[2024] EWHC 1929 (TCC)
[2024] EWHC 2890 (TCC)
[2024] EWHC 10 (TCC)