Bell Building Limited v TClarke Contracting Limited
[2024] EWHC 1929 (TCC)
A careful characterisation of the dispute referred is necessary in jurisdictional challenges, considering the underlying factual background.
Witney v Beam Construction [2011] EWHC 2332
The word 'dispute' should be given its ordinary English meaning, with a wide interpretation to preserve the adjudicator's jurisdiction.
Coulson on Construction Adjudication, 7.100 – 7.101
A single dispute is referred if the claim, containing several elements, can be described as a single, disputed claim for a sum due.
Coulson on Construction Adjudication, 7.123
The adjudicator's jurisdiction is determined by the terms of the notice of adjudication; they must only decide the issues referred.
Pentan v Spartafield [2016] EWHC 317 (TCC); McAlpine v Transco [2004] BLR 352 QBD (TCC)
Courts should be wary of excess of jurisdiction arguments, except in the plainest of cases.
Carillion v Devonport [2005] EWCA Civ 1358
The use of 'or such other amount' cannot be stretched to encompass claims for unliquidated damages.
Stellite v Vascroft [2016] BLR 402 QBD (TCC)
The Claimant's application for summary judgment succeeded.
The court found that only one dispute was referred, concerning the sums due under the payment application. The adjudicator's determination of 'true value' was within jurisdiction, as it was an alternative route explicitly requested in the referral notice.
[2024] EWHC 1929 (TCC)
[2023] EWHC 2344 (TCC)
[2024] EWHC 269 (TCC)
[2024] EWHC 2188 (TCC)
[2024] EWHC 750 (TCC)