Bellway Homes Limited v Surgo Construction Limited
[2024] EWHC 10 (TCC)
A contract must include written provisions enabling a party to give notice of intention to refer a dispute to adjudication and providing a timetable to secure adjudicator appointment within 7 days.
Housing Grants, Construction and Regeneration Act 1996 (HGCRA), s. 108(2)(a) and (b)
If a contract does not comply with HGCRA requirements, the adjudication provisions of the Scheme for Construction Contracts apply.
HGCRA, s. 108(5)
An adjudicator must act impartially.
HGCRA, s. 108(2)(e)
Any clause discouraging a party from referring a dispute to adjudication breaches the HGCRA.
Pioneer Cladding Ltd v John Graham Construction Ltd [2013] EWHC 2954 (TCC)
The contractual timescale must have the object of securing referral within seven days of the adjudication notice, but this is an objective, not a rigid requirement.
William Verry Ltd v North West London Communal Mikvah [2004] EWHC 1300 (TCC)
The adjudicator's jurisdiction derives from the agreement of the parties, as reflected in the contract. An adjudicator cannot be validly appointed under a non-existent contractual provision.
Twintec Ltd v Volkerfitzpatrick Ltd [2014] EWHC 10 (TCC)
If the identification of the correct contractual provisions makes no substantial difference to the adjudicator's jurisdiction, appointment, or procedure, a defence on this ground should be rejected.
Various cases discussed in sections 62-76
An adjudicator can order repayment of an overpayment as a dispositive remedy flowing from a re-evaluation of the true value of work.
S&T (UK) Ltd v Grove Developments Ltd [2018] EWCA Civ 2448
Mr. Cope was validly appointed, and his decision should be enforced.
The contractual adjudication terms did not contravene the HGCRA. The timetable for appointment, while potentially exceeding 7 days, had the object of securing appointment within that timeframe. The selection of an adjudicator from a pre-determined panel did not create a perception of bias.
Surgo is not entitled to the declaratory relief sought.
Bellway had a contractual right to recover the overpayment, supported by the construction of clause 4.9A, and general principles allowing for correction of overpayments in interim certificates. The adjudicator's decision to order repayment was within his jurisdiction.
[2024] EWHC 10 (TCC)
[2024] EWHC 1929 (TCC)
[2023] EWHC 2344 (TCC)
[2023] EWCA Civ 54
[2023] EWHC 2045 (TCC)