Caselaw Digest
Caselaw Digest

CNO Plant Hire Ltd v Caldwell Construction Limited

Two judges decided how much money one construction company owed another. The company that owed money argued they shouldn't have to pay because a different judge said the first judge was wrong. The court said the owing company has to pay first and fight the second decision later. They emphasized the importance of getting the money quickly to make things fair.

Key Facts

  • C.N.O Plant Hire Ltd (Claimant) and Caldwell Construction Ltd (Defendant) had a subcontract that did not comply with the Housing Grants, Construction and Regeneration Act 1996 adjudication requirements.
  • Three adjudications occurred: Mr. Latham's decision (5 March 2024) awarded £253,425.56 + interest to the Claimant; Mr. Lord's decision (14 April 2024) awarded £89,480.94 + VAT to the Claimant (partial payment made); a third adjudication (started 15 March 2023) is also mentioned.
  • The Defendant did not pay Mr. Latham's award and sought a set-off based on Mr. Lord's decision.
  • The dispute centered on whether the second adjudication was on the same or substantially the same subject matter as the first, and whether the court should allow a set-off despite the Defendant not seeking enforcement of Mr. Lord's decision.

Legal Principles

Enforcement of adjudication decisions: robust approach unless jurisdictional issues or breach of natural justice; immediate compliance with decisions unless otherwise directed; true valuation allowed only after compliance with payment obligations.

Bexheat Ltd v Essex Services Group Ltd [2022] EWHC 936 (TCC)

A party failing to pay a notified sum cannot commence a true value adjudication; preventing a paying party from commencing a true value adjudication on matters subject to a decision in the same payment cycle.

S&T (UK) Ltd v Grove Developments Ltd [2018] EWCA Civ 2448, Broseley London Limited v Prime Asset Management Limited [2020] EWHC 944 (TCC), Sudlows Limited v Global Switch Estates 1 Limited [2023] EWCA Civ 813, Lidl Great Britain v Closed Circuit Cooling Limited [2023] EWHC 3051 (TCC)

Set-off against adjudication awards is generally not permitted; exceptions include specified contractual rights, logical implication from the adjudicator's decision, and court discretion where two valid decisions involve payments owed by each party.

FK Construction Limited v ISG Retail Limited [2023] EWHC 1042 (TCC)

Steps for court consideration of set-off: validity of both decisions; enforceability of both decisions; enforcement of both decisions if valid and enforceable; appropriateness of set-off given the basis of the first decision.

HS Works Ltd v Enterprise Managed Services Ltd [2009] EWHC 729 (TCC)

Outcomes

The court refused to allow a set-off of Mr. Lord's award against Mr. Latham's award.

The Defendant did not bring enforcement proceedings for Mr. Lord's decision; the court considered it unfair and inappropriate to exercise its discretion to order a set-off in the absence of such proceedings; jurisdictional challenges concerning Mr. Lord's decision were anticipated; the court found the Defendant's argument of different payment cycles too simplistic; and allowing the set-off without first enforcing Mr. Latham's award would undermine the policy of swift adjudication enforcement.

Similar Cases

Caselaw Digest Caselaw Digest

UK Case Law Digest provides comprehensive summaries of the latest judgments from the United Kingdom's courts. Our mission is to make case law more accessible and understandable for legal professionals and the public.

Stay Updated

Subscribe to our newsletter for the latest case law updates and legal insights.

© 2025 UK Case Law Digest. All rights reserved.

Information provided without warranty. Not intended as legal advice.