Elements (Europe) Limited v FK Building Limited
[2023] EWHC 726 (TCC)
Corresponding date rule for calculating time periods in contracts.
Lewison on The Interpretation of Contracts (8th Ed), paragraph 15.10
Contract interpretation – courts interpret, they do not rewrite contracts.
Wood v Capita Insurance [2017] A.C. 1173 at [10] to [14]
Construction of contractual time limits – consideration of whether excluding public holidays or requiring notification on a business day is implied.
Elements (Europe) Limited v FK Building Limited [2023] EWHC 726 (TCC) at [40] to [42]
The court granted the claimant's declaration.
The notification of façade costs was served on July 3, 2023, one day after the four-month deadline calculated using the corresponding date rule. The court rejected the defendant's arguments to extend the deadline to include public holidays or to require notification only on a business day, emphasizing that the court interprets, but does not rewrite contracts. The court noted that a notification received on July 2nd would have been valid.
[2023] EWHC 726 (TCC)
[2023] EWHC 620 (TCC)
[2023] EWHC 1473 (TCC)
[2024] EWHC 591 (TCC)
[2024] EWCA Civ 962