Caselaw Digest
Caselaw Digest

Andrew Bellis v Sky House Construction Ltd

23 June 2023
[2023] EWHC 1473 (TCC)
High Court
Mr. Bellis fired his builder, but the judge said he did it too early according to their contract. Even though a previous official ruling said the builder was wrong, the judge agreed with the builder this time because of how the contract says time should be calculated.

Key Facts

  • Andrew Bellis (Claimant) terminated a construction contract with Sky House Construction Ltd (Defendant).
  • An adjudicator found the termination wrongful due to premature notice.
  • A second adjudication found Bellis liable for payment.
  • Bellis challenged the first adjudication's findings via a Part 8 claim.
  • The contract used the JCT Minor Works Building Contract 2016.
  • Clause 6.4 allowed termination for contractor default after a 7-day notice period.
  • Clause 6.2.3 specified notice delivery methods (hand delivery or recorded post).
  • Bellis served notices via email, but claimed hand delivery.
  • Clause 1.4 defined calculation of time periods as 'clear days'.
  • The adjudicator ruled the termination notice was one day early based on Clause 1.4.

Legal Principles

Court's robust approach to adjudication enforcement; only exceptionally challenged.

Global Switch Estates 1 Ltd v Sudlows Ltd [2020] EWHC 3314 (TCC), §44

Adjudicator's decisions enforced even with errors unless jurisdictional excess or serious natural justice breach.

Carillion v Devonport Royal Dockyard [2005] EWHC 778 (TCC), §80

Court interference with adjudicator's decision only in rare circumstances; pay now, argue later principle.

Carillion Construction Ltd v Devonport Royal Dockyard Ltd [2006] B.L.R. 15, §§85, 87; Macob Civil Engineering Ltd v Morrison Construction Ltd [1999] B.L.R. 93; Mead General Building Ltd v Dartmoor Properties Ltd [2009] EWHC 200 (TCC)

Exceptionally, a short, self-contained point requiring no oral evidence can be decided in a Part 8 claim for declaratory relief.

Caledonian Modular Ltd v Mar City Developments Ltd [2015] EWHC 1855 (TCC), [12]; Hutton Construction Ltd v Wilson Properties (London) Ltd [2017] EWHC 517 (TCC), §§17-19; Willow Corp. SÀRL v MTD Contractors Ltd [2019] EWHC 1591 (TCC), §§28-30

In Part 8 claims challenging adjudicator findings, the court's focus is on whether the adjudicator's decision was correct, not merely whether it contained an error.

Hutton Construction Ltd v Wilson Properties (London) Ltd [2017] EWHC 517 (TCC), §18; Willow Corp. SÀRL v MTD Contractors Ltd [2019] EWHC 1591 (TCC), §51

Outcomes

Defendant granted relief from sanctions for failing to file an Acknowledgement of Service.

Claimant not prejudiced; fully aware of Defendant's defence.

Claim dismissed.

Adjudicator correctly ruled termination notice unlawful due to premature service; Court found Clause 1.4 applied to the 7-day notice period, meaning the termination notice was sent a day early.

Similar Cases

Caselaw Digest Caselaw Digest

UK Case Law Digest provides comprehensive summaries of the latest judgments from the United Kingdom's courts. Our mission is to make case law more accessible and understandable for legal professionals and the public.

Stay Updated

Subscribe to our newsletter for the latest case law updates and legal insights.

© 2025 UK Case Law Digest. All rights reserved.

Information provided without warranty. Not intended as legal advice.