Bell Building Limited v TClarke Contracting Limited
[2024] EWHC 1929 (TCC)
Part 8 procedure is appropriate only where a question is unlikely to involve a substantial dispute of fact.
Civil Procedure Rules 1998, Rule 8.1(2)
Part 8 claims are typically used when there is no substantial dispute of fact, such as disputes over contract construction or statutory interpretation where primary facts are undisputed.
TCC Guide, Paragraph 3.3.2
The court has the power to order a Part 8 claim to proceed under Part 7 if deemed inappropriate.
CPR r.8.1(4)
In Part 8 claims, the question for the court must be framed with precision and be capable of a precise answer; there is a risk of inappropriate use leading to ill-informed decisions.
Merit Holdings Ltd v. Michael J. Lonsdale Ltd [2017] EWHC 2450 (TCC)
The court ruled that the Part 8 procedure was inappropriate.
The case involved substantial disputes of fact regarding the existence and terms of a contractual variation, requiring witness evidence. The court also noted that the claim was based on the flawed assumption of reviewing the adjudicator's decision, rather than independently determining the parties' rights.
The claim was directed to proceed under Part 7.
The court found that the Part 8 procedure risked ill-informed decisions and that TClarke had not identified precise legal questions for trial on agreed facts that would be determinative of the dispute.
[2024] EWHC 1929 (TCC)
[2023] EWHC 969 (TCC)
[2023] EWHC 3122 (TCC)
[2023] EWHC 301 (TCC)
[2024] EWHC 878 (TCC)