Caselaw Digest
Caselaw Digest

ISG Retail Limited v FK Construction Limited

18 April 2024
[2024] EWHC 878 (TCC)
High Court
Two construction companies were fighting over money. A judge decided there were too many disagreements about the facts, so he wouldn't make a decision using the simpler, faster Part 8 court process. Instead, the case will proceed through the more complex Part 7 process which allows for a full examination of the facts.

Key Facts

  • ISG Retail Limited (ISG) was the main contractor and FK Construction Limited (FK) was the subcontractor for the construction of six industrial units.
  • A dispute arose regarding FK's Application for Payment 21 (AFP21), specifically concerning an 188-day extension of time (EoT) and £198,000 in prolongation costs awarded to FK by adjudicator Mr. Molloy.
  • ISG argued that FK's entitlement to the EoT was conditional upon compliance with clause 9(5) of the subcontract, which FK allegedly breached.
  • FK denied breaching clause 9(5), alternatively arguing compliance, waiver, and estoppel.
  • ISG brought a Part 8 claim seeking declarations on the condition precedent nature of clause 9(5), FK's compliance, and the inapplicability of waiver/estoppel.
  • The parties have a history of extensive litigation.

Legal Principles

In Part 8 claims, the claimant must establish that a substantial factual dispute is unlikely.

CPR 8.1(2)

The court may convert a Part 8 claim to Part 7 proceedings if a substantial factual dispute arises.

CPR 8.1(4)

Part 8 proceedings are designed for determining claims without elaborate pleadings.

White Book 8.0.1; ING Bank NV v Ros Roca SA [2012] 1 WLR 472

Whether a contractual term is a condition precedent is a matter of construction.

Obrascon Huarte Lain SA v Her Majesty’s Attorney General for Gibraltar [2014] EWHC 1028 at [311]-[313]

A time limit clause may be directory rather than mandatory; breach may sound in damages, not a condition precedent.

Diab v. Regent Insurance Co Ltd [2007] 1 WLR 797 at [14]-[17]

Part 8 proceedings are generally unsuitable for trying estoppel issues.

ING Bank NV v. Ros Roca SA [2011] EWCA Civ 353

Requirements for estoppel by convention include a shared assumption, responsibility for the assumption, reliance, subsequent dealing, and detriment/benefit.

The Law of Waiver, Variation and Estoppel (3rd Ed 2012 Wilken & Ghaly) at paragraph 10.01; Jawaby Property Investment Limited v Interiors Group Ltd [2016] EWHC 557 (TCC)

Waiver can operate through equitable estoppel (pre-performance) or election to affirm (post-performance).

Westbrook Resources Ltd v Globe Metallurgical Inc [2009] EWCA Civ 310 at [12]

Outcomes

The Part 8 claim was dismissed.

The court found substantial disputes of fact likely regarding FK's breach of clause 9(5) and the applicability of waiver/estoppel. The court deemed it inappropriate to decide the construction points without addressing breach and waiver/estoppel simultaneously.

No declarations were made.

The presence of substantial factual disputes rendered the Part 8 procedure unsuitable.

Similar Cases

Caselaw Digest Caselaw Digest

UK Case Law Digest provides comprehensive summaries of the latest judgments from the United Kingdom's courts. Our mission is to make case law more accessible and understandable for legal professionals and the public.

Stay Updated

Subscribe to our newsletter for the latest case law updates and legal insights.

© 2025 UK Case Law Digest. All rights reserved.

Information provided without warranty. Not intended as legal advice.